In 2019, using both a heat and an equity index, a composite ranking list was created. This list helped determine the prioritization of a total of 55 schools who were without AC across the district. In 2020, a bond package passed and thanks to Denver voters, the first 24 schools on the list were given the necessary funding for AC upgrades.
The ranking for prioritization was determined by both a heat and an equity index.
The Equity Index is based on 3 sets of criteria: percentage of students classified as special education learners, percentage of students receiving free & reduced lunch, and the degree of volatility in conjunction with the Heat Index.
The Heat Index was developed through the DPS Planning, Design, and Construction team. The team measures the temperature of classrooms in buildings without cooling, and from that data develops an index of the hottest schools.
*Since the passing of the bond in 2020, we have spent $80 million dollars on school AC and cooling upgrades. By the end of our scheduled upgrades, we are forecasted to spend $129 million.*
As of 9/1/2023, all of the schools scheduled to receive their AC upgrades in 2023 have had their projects completed, bringing the total number of schools completed out of the bond package to 17.
17 schools out of the 24 schools identified in 2020 have received AC upgrades. The remaining 7 schools from the 2020 package will have their upgrades completed in 2024.
Schools that now have air conditioning:
Force [Force Elementary School] |
Grant [Grant Beacon Middle School] |
Smith [Smith Elementary School] |
Valverde [Valverde Elementary School] |
Fairview [Fairview Elementary School] |
Hallett [Hallett Academy] |
Merrill [Merrill Middle School] |
Ashley [Ashley Elementary School] |
Smedley [Denver Montessori Junior/Senior High School and Denver Online High School] |
West High School [West High School] |
Manual [Manual High School] |
Denison [Denison Montessori School] |
Fallis [Denver Green School Southeast] |
Smiley [McAuliffe International School] |
Rishel [KIPP Denver Collegiate High School] |
Columbine [Columbine Elementary School] |
Knapp [Knapp Elementary School] |
Schools to receive air conditioning in 2024:
Ebert [Polaris Elementary] |
Carson [Mary G Carson Elementary School] |
Cowell [Cowell Elementary School] |
Sabin [Sabin World Elementary School] |
Jefferson [Thomas Jefferson High School] |
Stedman [Stedman Elementary School] |
Steele [Steele Elementary School] |
The remaining schools excluded from the 2020 bond package that are without AC and without AC funding are of great importance to DPS, and we are actively seeking future funding opportunities.
For more information on heat mitigation measures, the composite ranking system and the current AC project schedule, please review our air conditioning FAQ and subscribe to our bond and mill levy newsletter.