2009

FOLDING LUNCHRM TABLES

001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES.

LEARNING LANDSCAPE

002 LEARNING LANDSCAPE - Complete LL -- install ampitheatre -- construct shade shelter -- erect gateway (slated2003 GOB, confirm) -- build crusher fines path and irrigation for community garden, install concrete benches.

2012

FIRE SUPPRESSION / SPRINKLER

001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPSDesign and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS andall other applicable DPS Standards. Patch and Repair.

2013

ADA COMPLIANCE

001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700:ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided.Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to theA/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to theareas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have notbeen identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS FacilityPlanning through the DPS Project Manager.

FINISH RESTORATION

001 FINISH RESTORATION / CARPET - Replace the item.