School Details
Stedman (277)
School Website | Bond Information for this School
2940 Dexter St. 80207
Tel: 303-322-7781
Fax: 720-424-3825
Principal: Deborah Johnson-Graham
Grade Levels: ECE - Grade 5
Full-Day Kindergarten: Yes
Kaleidoscope Corner: No
Magnet Program: No
Uniforms: No
Programs
Contact the school.
Bond Information
2009
FOLDING LUNCHRM TABLES
001 FOLDING LUNCHRM TABLES - INSTALL SURFACE MOUNTED POCKET TABLES.
LEARNING LANDSCAPE
002 LEARNING LANDSCAPE - Complete LL -- install ampitheatre -- construct shade shelter -- erect gateway (slated2003 GOB, confirm) -- build crusher fines path and irrigation for community garden, install concrete benches.
2012
FIRE SUPPRESSION / SPRINKLER
001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPSDesign and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS andall other applicable DPS Standards. Patch and Repair.
2013
ADA COMPLIANCE
001 ADA COMPLIANCE - LEVEL 1 - Comply with DPS Design and Construction Standards SECTION 00700:ACCESSIBILITY STANDARDS and all other applicable DPS Standards. See ADA Level 1 Database provided.Deficiency remedies provided in ADA database should serve as the PM guide only and should not be provided to theA/E for purposes of developing the project scope of work. A/E is directed to conduct a building survey limited to theareas identified in the survey. Other ADA deficiencies may be included if they meet the level 1 status and have notbeen identified in the survey. All questions of possible oversight of a deficiency shall be directed to DPS FacilityPlanning through the DPS Project Manager.
FINISH RESTORATION
001 FINISH RESTORATION / CARPET - Replace the item.







