School Details

Montclair School of Academics & Enrichment (257)

School Website | Bond Information for this School

1151 Newport St. 80220
Tel: 303-333-5497
Fax: 720-424-5405

Principal: Shannon Hagerman

Grade Levels: ECE - Grade 5

Full-Day Kindergarten: Yes
Kaleidoscope Corner: No
Magnet Program: No
Uniforms: No



Programs

Contact the school.


Bond Information

2009

LUNCHROOM TABLES

002 REMOVE AND REPLACE CAFETERIA TABLES.

ROOFING

008 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlitewith 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2"polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhaustscurbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipeand similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace andseal all existing pipe collars. Inspect/replace all applicable drains and gutters.

009 ROOFING - BUILT-UP - Built-Up roofing to include the following: Gravel, 4-ply membrane,replace existing perlitewith 1/2" wood fiber, 1/8" taper insulation, replace exsiting polyisocyanurate insulation with 2 layers of 2"polyisocyanurate insulation, replace flashing per DPS specs at all walls, drains, conduits, flues, gas lines, exhaustscurbs, thru-wall and overflow scuppers, skylights, A/C lines, expansion joints, and parapets. Replace all gaspipeand similiar stand supports bases with concete pavers, paint all existing gas piping per DPS specs. Replace andseal all existing pipe collars. Inspect/replace all applicable drains and gutters.

BUILDNG (NEW)

001 PLACE MODULAR CLASSROOMS FOR ECE EXPANSION FULL DAY PROGRAMS

2010

IRRIGATION

001 IRRIGATION - Replace existing irrigation system, piping, controls, heads, backflows, electrical and connectionsper DPS standards. - Montclair - Add 1 central clock. Site area to include all lawn areas around main building andapproximatley 35,000 sf. Include right of way replacement/installation. Work to be conducted in conjunction withlearning landscape project. See DPS Planning for site plans and QA/QC evaluations/recommendations.

LEARNING LANDSCAPE

001 LEARNING LANDSCAPE - Construct Learning Landscape per UCD Master Plan. Include 2" playground surfaceasphalt overlay. Work should be coordination with irrigation project . See master plan draft atwww.learninglanscapes.org - Conduct soils asphalt and other pertinent testing prior to bid development.

2011

FIRE SUPPRESSION / SPRINKLER

001 FIRE SPRINKLER SYSTEM - Design new fire sprinkler system throughout entire building. Comply with DPSDesign and Construction Standards SECTION 15300: STANDPIPE AND FIRE SPRINKLER STANDARDS andall other applicable DPS Standards. Patch and Repair.